Delek Starts 10-Day Big Spring Refinery Maintenance

Delek Starts 10-Day Big Spring Refinery Maintenance

DAVENPORT, FL (DTN) — Delek US Holdings began a 10- day planned maintenance on Monday (10/5) at its 73,000 bpd Big Spring refinery in Texas involving the fluid catalytic cracking unit (FCCU), dieesel hydrotreater and ultra-low-sulfur gasoline unit, according to a filing with the Texas Commission on Environmental Quality (TCEQ).

The maintenance is scheduled from 8 a.m. CT Monday through Thursday, October 15,  8 a.m. CT and involves routine work on refinery equipment, according to the filing.

Delek expects emissions associated with the work from the FCCU regenerator vent and the refinery’s North and South flares. The filing estimates 5,001 pounds of carbon monoxide and 501 pounds of sulfur dioxide from the FCCU regenerator, along with an estimated 4,451 pounds of sulfur dioxide from the two flares.

The work includes units important to refined products production. The FCCU is a key gasoline-producing unit, while the diesel hydrotreater is used to remove sulfur from diesel fuel and the ULSG unit is associated with production of low-sulfur gasoline.

The scheduled work follows an August event involving the refinery’s FCCU, when a carbon-monoxide boiler malfunction led the unit to be placed in full burn and resulted in an estimated 5,001 pounds of carbon monoxide emissions.

The Big Spring refinery primarily produces gasoline, diesel and other transportation fuels.

DTN reached out to Delek US Holdings for additional details but did not get an immediate response.

(c) Copyright 2026 DTN, LLC. All rights reserved.